Requirements can be managed either locally in Klaros-Testmanagement or in a remote system.
Local Requirements Management |
By default, test managers can create, edit, and delete requirements for a project from within the project. |
Remote Requirements Management |
A project can also receive its requirements from an external requirement management system (RMS). If this is configured, the creation, editing and deletion of requirements can only be done via the connected RMS. |
Currently Klaros-Testmanagement supports the following external requirement management systems:
Jira 4.3 or newer |
A commercial issue management system produced by Atlassian Pty Ltd., see
|
The table shows the following values:
ID |
Assigned automatically. |
Additional Information |
A tooltip appears when the cursor is placed over the icon shown here. the requirement management system be deleted because it is connected with at least one project. no credentials for background synchronization has been provided. |
System |
The used requirements management system (Jira Version 4.3 or higher). |
URL |
The link to the requirement management system. |
External Project ID |
See Section 10.5.1.1, “External Project ID”. |
Description |
A short description of the requirement management system. |
Projects |
The projects in which the issue management system is used. |
Actions |
The executable actions. |
By clicking on the button
a new empty table row will appear. All attributes of the requirement management system can be defined here.With
the requirement management system is saved. The ID of the requirement management system (RM00001) is automatically assigned by Klaros-Testmanagement.With
several table rows can be created and edited at the same time. Only when clicking on the data is stored in the database.With
all changes are undone.Red IDs | |
---|---|
All rows with red IDs have been changed and are not yet saved! |
The following actions can be performed in the action column:
Synchronizing Attachments | |
---|---|
When connected to a Jira server, attachments from its requirements are automatically transferred to Klaros-Testmanagement during synchronization. |