Unable to change the Test Environment and the System Under Test option

Miguel Calvimonte, geändert vor 4 Jahren.

Unable to change the Test Environment and the System Under Test option

Youngling Beitrag: 1 Beitrittsdatum: 08.05.20 Neueste Beiträge
Hi,
When attempting to create or modifying the Latest Success Rate or the Latest Activity reports on the dashboard, is not possible to change the values of the Test Environment and the System Under Test lists in the options. Is this a bug or a limitation of the Community Edition of Klaros?

Best regards,
Miguel
thumbnail
Torsten Stolpmann, geändert vor 4 Jahren.

RE: Unable to change the Test Environment and the System Under Test option (Antwort)

Jedi Council Member Beiträge: 759 Beitrittsdatum: 12.02.09 Neueste Beiträge
Hi Miguel,

this is a limitation of the community edition. The enterprise edition lets you choose these parameters as well as the project/iteration of the dashboard report.

Hope this helps.

Regards,

Torsten